Concrete volume and bag calculator

Estimate concrete for slabs, cylinders and round post holes. Convert to cubic yards or metres, add allowance and calculate bags using your product’s mixed yield.

Only this page link is shared. Your text, files and results are not included.

Use your browser to add this page to its bookmarks. This button shows the steps; it does not add a bookmark automatically.

Windows / Linux
Ctrl + D
Mac
⌘ + D

On your phone or tablet

Open your browser’s menu or Share menu and choose Add bookmark or Add to Favorites. In an in-app browser, open this page in your usual browser first.

Bookmarks save the page link, not your tool inputs or results. “Save as favorite” is a separate list within BIJJO.

Runs in your browser. Files are not uploaded.

Calculated on your device. No uploads or account.

Units appear beside each measurement. Switching units reinterprets existing numbers; it does not convert them. Currency display does not convert prices.

Yield is the volume of mixed concrete stated on the product label, not bag weight. No mix ratio, water quantity, reinforcement or foundation sizing is prescribed. Price excludes delivery, tax and labour.

Enter measurements and product details, or try an example.

How to use

Add sections with their measured dimensions and counts. For a round post hole enter outer and inner diameters. Choose allowance, ready-mix volume or labelled bag yield and an optional price.

Calculation rules

Slab volume = length × width × thickness. Cylinder = π × diameter² × height ÷ 4. Round hole around a post subtracts the inner cylinder. Sum sections, apply allowance, then divide by yield and round bags up. Bulk volume remains unrounded for cost calculation.

Scope and limits

Quantity estimate only. You supply all dimensions and product yield. The tool does not design foundations, specify concrete strength, mix proportions, reinforcement, post depth or load capacity. Cement alone is not premixed concrete. Irregular excavation, compaction and supplier minimums/rounding are not included.

Worked example

A 3 × 2 m slab at 10 cm thickness is 0.6 m³. With 10% extra it needs 0.66 m³ (660 L). An illustrative label yield of 20 L per bag needs 33 bags; at 6 each, material cost is 198.